ποΈ Fayna Town keeps growing, and some buildings are already moving from the construction site to housewarmings.
As of the beginning of August, several important stages are underway at once: apartment viewings are already taking place in Buildings No. 40, No. 41, and No. 42; Buildings No. 23, No. 24, and No. 24a are actively moving on to facade and finishing works; and phase 12 is gaining height.
We have gathered the current status of works for each building π
π Buildings No. 40, No. 41, No. 42:
The buildings have been commissioned, and all through July we have been meeting our Fayna investors at apartment viewings. Everything is 100% complete. See you in your new home!
ποΈ Building No. 23
β’ Structure: Foundation (piles + 450 mm slab), monolithic frame, stairs, ventilation blocks, and wall masonry β 100%.
β’ Facade and roof: Roofing β 100%. REHAU windows are fully installed β 100%
Facade insulation β 95%. Installation of aluminum composite panels is underway. Glazing system β 70% (+20% over the month!)
β’ Interior works: Floor screeds β 80%.
β’ Finishing: wall plaster β 40%, ceramic tile installation β 25%
β’ Networks and equipment: Elevators installed β 100%. Ventilation β 100%.
β’ Electrical networks β 90%, water supply β 90%, sewage β 90%, heating system β 75%. Video surveillance and access control β 70%, fire-protection systems β 40%
ποΈ Building No. 24
β’ Structure: Foundation (piles + slab), monolith, stairs, and ventilation blocks β 100%. Wall masonry β 90%.
β’ Facade and roof: Roofing β 95%. Facade insulation β 40%
β’ REHAU window installation β 30%. Installation of metal railings for the balconies and the roof has started β 10%.
β’ Networks: Ventilation β 90%, intercom network β 10%.
ποΈ Building No. 24a
β’ Structure: Foundation, monolith, stairs, ventilation blocks, and wall masonry β 100%
β’ Facade and roof: Roofing β 100%. REHAU windows β 98%. Metal railing structures β 100%. Facade insulation β 50%.
β’ Interior works: Floor screeds β 70%
β’ Networks: Ventilation β 90%, intercom network β 40%. The tower crane has been dismantled
ποΈ Building No. 43 (phase 12)
β’ Structure: Excavation pit, piles, and waterproofing of the underground part β 100%
β’ Monolithic frame β 40% (4th floor of 9). Installation of ventilation blocks and reinforced-concrete stairs β 20%
A tower crane is operating on site.
ποΈ Building No. 44 (phase 12)
β’ Structure: The below-grade works are fully complete β 100%. The monolith crew is erecting floors 2β3 of the 16-story sections
β’ Two tower cranes provide parallel concreting of the sections
ποΈ Building No. 45 (phase 12)
β’ Structure: Excavation pit and piles β 100%. The basement slab is complete, and waterproofing of the underground part has been installed.
β’ Monolithic structures of the 1st floor are being erected
ποΈ Building No. 46 (phase 12)
β’ Structure: Below-grade works β 100%. Floors 1β2 of the 16-story sections have been erected, and the structures of the next floor are being installed
β’ Concreting is on schedule, and the frame is rising at a pace of one floor per month.