KAN
Menu
Укр
Eng
13.10.2025

News from the construction site of the Fayna Town Residential Complex

News from the construction site of the Fayna Town Residential Complex
🏗Building 38 Frame and foundation: The foundation is in place (225 piles, a 450 mm slab), the monolithic frame (3185 m³ of concrete, 314 tonnes of reinforcement), brick niches (93,6 m³), partitions (870 m²), and stair flights (33 pcs.). Facade and roof: Walls of aerated concrete blocks (586 m³) and the inverted roof are complete. Insulation is 100% complete, plastering and painting — 100%. Installation of REHAU windows (1820 m²) and porcelain stoneware (757 m²) is 100% complete. Air-conditioner baskets (139 pcs.) are 100% complete, balcony railings (255 m²) — 95%, balcony finishing — 100%. Interior works: All works (plaster, tile, 80 mm screeds, waterproofing, ceilings) are 100% complete. Fire doors (93 pcs.) are 100% installed. Engineering networks: Installation of 3 Otis elevators, the individual heating point, the water supply, the sewage system, the fire-protection systems, and the electrical cables is complete. Light fixtures are 100% installed, video surveillance — 100%. Cleaning and landscaping: Final cleaning and washing of the walls, floors, and windows of common areas (common-area cleaning) has begun; completion status — 90%. Landscaping is almost finished; cutting the paving slabs up to the building in individual places remains. Completion status — 80%. 🏗Building 39 Frame and foundation: Work on the foundation (151 piles, a 450 mm slab), the frame (3019 m³ of concrete, 397 tonnes of reinforcement), the ventilation shafts (18 m³), the partitions (680 m²), and the stairs (29 flights) is complete. Facade and roof: Walls (545 m³ of aerated concrete blocks) and the roof are complete. Insulation (3635 m²) is 100% complete, decorative plaster (3635 m²) — 95%. Installation of REHAU windows (2220 m²) is complete. Porcelain stoneware (276 m²) is 100% complete, air-conditioner baskets (151 pcs.) — 80%, railings (594 m²) — 30%, balcony finishing — 100%. Interior works: Installation of the fire doors (74 pcs.), plastering, tiling, screeds, and waterproofing are 100% complete. Engineering networks: 2 Otis elevators have been installed. Installation of the individual heating point, the water supply, the sewage system, and the fire-protection systems is complete. Electrical cables are 99% laid, light fixtures are 100% installed, video surveillance — 100%. Cleaning: Final cleaning and washing of the walls, floors, and windows of common areas (common-area cleaning) has begun; completion status — 60%. 🏗Building 40 Frame and foundation: Frame installation is complete (267 piles, 2721 m³ of concrete, 327 tonnes of reinforcement), as are the brick channels (20 m³), partitions (640 m²), and stairs (38 flights). Facade and roof: Walls of aerated concrete blocks (850 m³) and the roof are complete. Insulation (4330 m²) is 80% complete. REHAU windows (1755 m²) are 100% installed. Air-conditioner baskets (199 pcs.) are 80% complete, 1st-floor glazing — 100%. Interior works: Fire doors (93 pcs.) are 100% installed, service hatches — 95%. Plastering works are 95% complete. Floor screeds — 100%. Engineering networks: Otis elevators (4 pcs.) are 90% installed. Electrical cables are 95% laid, heating networks — 100%, water supply — 100%, sewage — 100%, fire-protection systems — 90%. 🏗Building 23 Work is proceeding on schedule, and we are proud to show a high pace and uncompromising quality at every stage. To date we have achieved significant results, laying the groundwork for your future comfort and safety. The foundation is 100% complete. We can say with confidence that our building stands on an unshakable foundation. Thanks to bored injection pile technology and a powerful monolithic reinforced-concrete slab with a thickness from 450 mm, we have secured maximum stability and durability of the entire structure for decades to come. The monolithic frame is 95% complete. In parallel, installation of the precast reinforced-concrete stair flights and ventilation blocks is 90% complete. We are actively working on erecting the external and internal walls (70% complete). Installation of Rehau windows has begun (30% complete). Installation of the sewage system has begun; 10% is complete. Move to 🔷KAN!
Looking for land lots for new projects

Chatbot for quick contact:

Subscribe to our updates:

2026  All right reserved «KAN DEVELOPMENT» LLC