Building 227
Monolithic works — 100%
Masonry works — 100%
Screed installation — 99%
Electrical works — 88%
Plumbing works — 90%
Ventilation installation — 100%
Roofing works — 100%
Plastering works — 95%
Installation of translucent structures — 100%
Facade works — 80%
External networks installation — 99.7%
Landscaping — 15%
Building 228
Monolithic works — 100%
Masonry works — 100%
Installation of translucent structures — 100%
Electrical works — 99.4%
Plumbing works — 99.5%
Ventilation installation — 99.5%
Painting works: 22802, 22803 — 99%, 22801 — 99%
Tiling works: 22802, 22803 — 100%, 22801 — 99%
Apartment door installation — 100%
Screed installation — 100%
Roofing works — 100%
Plastering works — 100%
Facade works — 94%
External networks installation — 80%
Landscaping — 15%
Building 229
Monolithic works — 35%
Building 230
Monolithic works — 91%
Masonry works — 90%
Roofing works — 90%
Installation of translucent structures — 94%
Screed installation — 72%
Electrical works — 25%
Plumbing works — 20%
Elevator equipment installation — 45%