Heavy machinery is hard at work, internal systems are being installed, and façades are taking shape. Yet behind all this activity, the future is already coming into view: morning coffee in your own kitchen, evening walks around the neighbourhood, and the first housewarming celebrations.
Here is how construction is progressing across the new phases of Respublika Residential Complex:
🏁 Building 230
Structural, masonry, and roofing works are 100% complete. The floor screed is finished, the windows are installed, and the lifts are nearly complete at 97%. The building’s inner systems are now coming to life: ventilation is at 97%, plastering at 90%, tiling at 85%, and electrical works at 79%. The façade is already 64% complete. This building is confidently entering the final stretch ✨
⚙️ Building 229
The structural frame is nearly complete at 95%, while the walls continue to rise, with masonry works at 65%. Window installation is at 37%, and roofing works are at 33%. Internal systems are also underway: ventilation is at 60%, while plumbing and electrical works, both at 10%, are only beginning to gain momentum. The most exciting stages are still ahead.
🌱 Buildings 305 and 306
305: The piling works are 100% complete, and structural works have begun at 15%. The reinforced concrete frame is actively rising across all sections.
306: Piling works are 100% complete, and structural works are at 5%. The first floors are just around the corner.
🚧 Building 307
Piling works are at 33%, and the pace remains strong. The construction site is actively preparing for the next stage.
🅿️ Parking Facility 22
Piling works are 100% complete, while standalone foundations are 90% finished. A future space for your car is already taking shape.
Every percentage point brings us one step closer to moving day. And we are moving towards it every day 🔑
Create with 🔷 KAN!