15.01.2026

Construction progress of the Respublika residential complex for December.

Construction progress of the Respublika residential complex for December.
πŸ— Building 227 Monolithic works β€” 100% complete Masonry works β€” 100% Floor screed installation β€” 100% Electrical works β€” 98% Elevator equipment installation β€” 100% Plumbing works β€” 98% Ventilation installation β€” 100% Roofing works β€” 100% Plastering works β€” 100% Finishing works β€” 95% Installation of glass structures β€” 100% Facade works β€” 95% External utilities installation β€” 100% Landscaping β€” 40% πŸ— Building 228 Monolithic works β€” 100% complete Masonry works β€” 100% Installation of glass structures β€” 100% Electrical works β€” 100% Elevator equipment installation β€” 100% Plumbing works β€” 100% Ventilation installation β€” 100% Painting works: 22802, 22803 β€” 100%, 22801 β€” 100% Tiling works: 22802, 22803 β€” 100%, 22801 β€” 100% Apartment door installation β€” 100% Floor screed installation β€” 100% Roofing works β€” 100% Plastering works β€” 100% Facade works β€” 100% External utilities installation β€” 100% Landscaping β€” 80% πŸ— Building 229 Monolithic works β€” 65% complete Masonry works β€” 38% πŸ— Building 230 Monolithic works β€” 100% complete Masonry works β€” 99% Roofing works β€” 100% Facade works β€” 31% Installation of glass structures β€” 100% Floor screed installation β€” 100% Electrical works β€” 55% Plumbing works β€” 42% Elevator equipment installation β€” 91% Create with πŸ”·KAN!
Looking for land lots for new projects

Π§Π°Ρ‚-Π±ΠΎΡ‚ для швидкого звʼязку:

Subscribe to our updates:

2026 Β All right reserved Β«KAN DEVELOPMENTΒ» LLC