We all especially need good news right now, so we're sharing Fayna Town's construction progress for December. While they destroy — we create ❤️🫂
🏗Building 40:
The building is on the home stretch, with a high degree of readiness across all systems.
* Structure: Monolithic frame (267 piles, 2721 m³ of concrete, 327 t of reinforcement), brick ventilation shafts (20 m³), partitions (640 m²), and stairs (38 flights) — 100% complete
* Facade: Walls (850 m³ of aerated concrete block) and the roof are complete. Insulation has reached 90%. REHAU windows, 1st-floor glazing — 100%, air-conditioner baskets — 95%
* Interior: Plaster, screeds, and fire doors — 100%, service hatches — 95%. Fine tile finishing of the 1st floors has begun (30%)
* Networks: Electricity, heating, water, and sewage — 100%. Fire-protection systems — 95%, Otis elevators — 95%
🏗Building 23:
Special attention to the new construction phase! Work here has sped up, showing excellent results
* Foundation: 100% complete (bored injection piles + a 450 mm slab)
* Frame: The monolith is fully complete — 100%. Stair flights and ventilation blocks are also 100% installed
* Walls and windows: Wall masonry has reached 85%, installation of REHAU windows — 80%
* Networks: Sewage is 35% complete, and electrical networks are being actively laid. Roofing works have begun - 10%
🏗Building 41:
* Structure: The frame is fully complete (174 piles, 3551 m³ of concrete, 590 t of reinforcement), shafts (10 m³), partitions (1050 m²), and stairs (31 flights)
* External envelope: Walls (844 m³) and the roof are complete. Facade insulation — 77%. REHAU windows, doors, and 1st-floor storefronts are 100% installed. Air-conditioner baskets — 48%
* Interior works: Screeds — 100%, doors and hatches — 97%. Plaster and tile are 75% complete
* Networks: Radiators and 2 elevators have been installed. The individual heating point is 98% complete. Electricity, heating, water, sewage, and fire safety — readiness level 90%
🏗Building 42:
* Structure: Monolithic frame (296 piles, 4081,5 m³ of concrete, 490,5 t of reinforcement) and stairs (49 pcs.) — complete. Partitions (1400 m²) and shafts (81 m³) are 97% complete
* Facade: Walls (1500 m³) and the roof are at the 98% stage. Facade insulation is 85% complete, REHAU windows — 98%
* Networks: Ventilation blocks and elevators (4 pcs.) — 100% and 98%, respectively. Electrical installation (82%) and sewage installation (74%) are underway