While you picture your first morning in a new apartment at the Fayna Town residential complex, the KAN team is bringing that morning closer, step by step ☕🏗️
Every percent of readiness, every installed elevator, and every completed floor is not just a construction stage, but care for the future comfort of residents ❤️
We're sharing the progress for January:
🩷🩷 Building 40
The building is on the home stretch, with a high degree of readiness across all systems.
* Structure: Monolithic frame (267 piles, 2721 m³ of concrete, 327 t of reinforcement), brick ventilation shafts (20 m³), partitions (640 m²), and stairs (38 flights) — 100% complete.
* Facade: Walls (850 m³ of aerated concrete block) and the roof are complete. Insulation has reached 90%. REHAU windows, 1st-floor glazing — 100%, air-conditioner baskets — 95%.
* Interior: Plaster, screeds, and fire doors — 100%, service hatches — 95%. Fine tile finishing of the 1st floors has begun (45%).
* Networks: Electricity, heating, water, and sewage — 100%. Fire-protection systems — 95%, Otis elevators — 95%.
🩷🩷 Building 23
Work on the new construction phase is moving at a high pace.
* Foundation: 100% complete (bored injection piles + a 450 mm slab).
* Frame: The monolith is fully complete — 100%. Stair flights and ventilation blocks are also 100% installed.
* Walls and windows: Wall masonry has reached 90%, installation of REHAU windows — 85%.
* Networks: Sewage is 40% complete, and electrical networks are being actively laid. Roofing works have begun - completion 20%.
🩷🩷 Building 41
* Structure: The frame is fully complete (174 piles, 3551 m³ of concrete, 590 t of reinforcement), shafts (10 m³), partitions (1050 m²), and stairs (31 flights).
* External envelope: Walls (844 m³) and the roof are complete. Facade insulation — 77%. REHAU windows, doors, and 1st-floor storefronts are 100% installed. Air-conditioner baskets — 48%.
* Interior works: Screeds — 100%, doors and hatches — 97%. Plaster and tile are 75% complete.
* Networks: Radiators and 2 elevators have been installed. The individual heating point is 98% complete. Electricity, heating, water, sewage, and fire safety — readiness level 92%.
🩷🩷 Building 42
* Structure: Monolithic frame (296 piles, 4081,5 m³ of concrete, 490,5 t of reinforcement) and stairs (49 pcs.) — complete. Partitions (1400 m²) and shafts (81 m³) are 98% complete.
* Facade: Walls (1500 m³) and the roof are at the 98% stage. Facade insulation is 85% complete, REHAU windows — 98%.
* Networks: Ventilation blocks and elevators (4 pcs.) — 100% and 98%, respectively. Electrical installation (83%) and sewage installation (79%) are underway.