A city you want to live in starts with the details. And today those details are appearing in every square meter of the Respublika residential complex. Where scaffolding stood only yesterday, tomorrow there will be windows with a view, cozy evenings, and new traditions. Here is how construction of Buildings 227 and 228 is progressing now:
🏗 Building 227
Monolithic works — 100%
Masonry works — 100%
Installation of translucent structures — 100%
Roofing works — 100%
Ventilation installation — 100%
External networks — 98%
Plastering — 75%
Screed — 70%
Electrical installation — 55%
Plumbing — 55%
Facade — 45%
Landscaping — preparatory work is underway
🏗 Building 228
Monolithic works — 100%
Masonry — 100%
Screed — 100%
Plastering — 100%
Roof — 100%
Translucent structures — 100%
Tile:
▪️ 228.02, 228.03 — 100%
▪️ 228.01 — 90%
Painting works:
▪️ 228.02, 228.03 — 98%
▪️ 228.01 — 90%
Doors — 99.5%
Plumbing — 99%
Ventilation — 99%
Electrical installation — 98%
Facade — 85%
External networks — 40%
Landscaping — preparatory work is underway