We are sharing the latest construction progress at the Respublika residential complex.
π Building No. 230
Construction is approaching the final stage.
Monolithic works β 100%
Masonry works β 100%
Roofing works β 100%
Screed installation β 100%
Window installation β 100%
Elevator installation β 97%
Ventilation installation β 97%
Plastering works β 90%
Heating and water supply β 80%
Tile laying β 95%
Electrical installation works β 82%
Facade works β 75%
Landscaping β 20%
βοΈ Building No. 229
The building is actively taking shape. Interior engineering works are underway in parallel.
Monolithic frame β 95%
Masonry works β 75%
Window installation β 50%
Roofing works β 40%
Ventilation installation β 60%
Plumbing works β 20%
Electrical installation works β 20%
Elevator installation β 20%
Installation of entrance groups β 15%
π± Building No. 305
Pile field β 100%
Monolithic works β 20%
The frame is steadily rising in every section, and the building is gradually gaining height.
π± Building No. 306
Pile field β 100%
Monolithic works β 12%
Construction of the first floors is very close. Work continues at the planned pace.
π§ Building No. 307
Pile field β 60%
We are preparing the base for the next stage of construction.
π
ΏοΈ Parking No. 22
Pile field β 100%
Isolated foundations β 100%
Monolithic frame β 12%
The parking structure is gradually taking shape.
Every completed stage brings the housewarming closer. Thank you for creating the future with us! π