Construction progress in detail:
🏗Building 23
Work is underway on several fronts at once: from the facade to engineering and equipment installation.
Structure:
foundation, piles, and a 450 mm slab — 100%;
monolithic frame — 100%;
stairs, ventilation blocks, and wall masonry — 100%.
Facade and roof:
roofing — 100%;
REHAU window installation — 95%;
facade insulation — 15%.
Interior works:
floor screed installation — 25%.
Utilities and equipment:
sewage — 85%;
electrical networks — 70%;
water supply — 40%;
heating system — 55%;
elevator installation — 70%.
🏗Building 24a
The building is rising at a confident pace: the main structure is already complete, and facade and engineering works continue.
Structure:
foundation — 100%;
monolith — 100%;
stairs and ventilation blocks — 100%;
wall masonry — 80%.
Facade and roof:
roof slope-forming layer — 100%;
PVC membrane laying — 30%;
REHAU window installation — 30%;
facade and loggia insulation — 2%.
Utilities:
sewage — 30%;
electrical networks — 10%.
🏗Building 24
The main structural works in the building are complete, and wall masonry continues.
Structure:
foundation, piles, and slab — 100%;
monolith — 100%;
stairs and ventilation blocks — 100%;
wall masonry — 30%.
🏗Building 40
The building is already at the final stage of work. The main structural, facade, and engineering processes are done, and the final touches are underway.
Structure and interior:
monolith — 100%;
ventilation ducts, partitions, and stairs — 100%;
rough finishing — 100%;
fire doors — 100%;
tiling on the 1st floor — 100%.
Facade:
walls, roofing, windows, and 1st-floor curtain walls — 100%;
facade insulation and air-conditioner baskets — 95%;
balcony glazing — 10%.
Utilities and equipment:
electricity, heating, water, sewage — 100%;
fire-safety systems — 100%;
Otis elevators — 100%.
🏗Building 41
The building is moving into the fine-finishing stage. The external envelope is almost complete, and the utility networks are also at a high level of readiness.
Structure and external envelope:
frame, walls, roofing, glazing, and 1st-floor storefronts — 100%;
facade insulation — 80%;
air-conditioner baskets — 52%.
Interior works:
screeds — 100%;
doors and service hatches — 100%;
plastering and tiling — 88%.
Utilities and equipment:
radiators — 100%;
2 elevators — 100%;
individual heating point — 99%;
engineering networks package: electricity, water, heating, fire safety — 95%.
🏗Building 42
The building is in an active phase of work. The main structure is complete, and the facade and engineering are quickly approaching a high level of readiness.
Structure:
frame — 100%;
stairs, partitions, and ducts — 100%.
Facade:
walls, roofing, and REHAU windows — 98%;
facade insulation — 92%.
Utilities and equipment:
ventilation blocks — 100%;
4 elevators — 99%;
sewage — 93%;
electrical wiring — 86%.