Hi, it's me - UNIT.Home ๐๏ธ
I am growing, changing and getting closer to my residents. Someone already has the keys in their pocket, someone is planning the kitchen design, and I continue to work on the details. Watch how my construction is progressing - section by section, brick by brick.
Construction progress in March:
๐ House 07
โ
All apartments have been handed over to the owners
๐ง Repairs are underway
๐ก More and more residents are already enjoying life in the most innovative project in Ukraine
๐ House A05
๐ The final stage of key handover
๐ง The first future residents have already started repairs
๐ Central Tower
๐ The final stage of the key handover
๐ง Repairs in the first apartments have started
๐ House A06
๐น Section A0601:
Installation of a hinged ventilated facade - 33%
Fire partitions in elevator halls - 100% of double-glazed windows installed
Installation of balcony fence brackets - completed
Preparation of the walls and ceilings of the MZK for painting - completed
๐น Section A0602:
Facade - 39% completed
Installation of glass balcony railings - 100% of brackets installed
Hatches and doors of flush-mounted MZK - completed
Fire partitions - 100% of double-glazed windows
Insulation of walls and ceilings of vestibules - completed
Preparation of walls and ceilings of the MZK for painting - completed
๐น Sections A0603-A0604:
Facade - 27% complete
Brackets for balcony fences - 76% complete
Insulation of vestibules - completed
Preparation of the walls and ceilings of the MZK for painting - completed
๐น Section A0605:
Flush-mounted hatches - 72% completed
Installation of cold passage doors - completed
Brackets for balcony fences - 79% complete
Facade