In Faina Town, the hot season continues even in January! The buildings are growing, the facades are getting their final look, and the final touches of comfort are already appearing inside. A little more time and the new apartments will open their doors to their owners.
Fresh construction update:
38th house
- Installation of railings and fences on the staircases has begun.
- We are working on the facade insulation. The completion status is 95% and we are finishing the facade walls - 25%.
- Finishing works on the walls of the parking lot - 100% complete
- We are working on the installation of paving slabs
39th house
- Works are underway to insulate the walls of the facade of the house - 70%
- We are finishing the walls and floors with ceramic tiles on the floors 2-16 - 85%.
- We started installing ceramic tiles in the lobby of the 1st floor
- We are carrying out internal engineering works, namely water supply, sewerage, and electricity. The status of execution is 95%.
- Installation and glazing of exterior stained-glass windows on the 1st floor of the building is 100% complete
40th house
- Stone works - 80%.
- Roofing works - 85%.
- Installation of translucent structures - 70%.
- Installation of elevator equipment - 100%. Internal networks - 20%.
- We have started interior decoration, the status of execution is 15%.
41 houses
- Installation of cement sand screed - 40%.
- Roofing works started in January - 5%.
- Installation of entrance apartment doors and installation of apartment radiators started. 2-8 floors.