🏗 Building 229
Monolithic structural works are 89% complete
Masonry works — 51%
Installation of translucent structures — 22%
Ventilation system installation — 57%
Plumbing works — 7%
Electrical installation works — preparation stage
🏗 Building 230
Monolithic structural works — 100%
Masonry works — 100%
Roofing works — 100%
Facade works — 44%
Installation of translucent structures — 100%
Floor screed works — 100%
Ventilation system installation — 97%
Electrical installation works — 71%
Plumbing works — 60%
Plastering works — 85%
Tiling works — 75%
Elevator equipment installation — 97%
🏗 Building 305
Pile foundation works — 100%
Monolithic structural works — 10%
Construction of the reinforced concrete frame is actively progressing across all sections.
🏗 Building 306
Pile foundation works have been completed for all sections. Construction of the monolithic reinforced concrete foundations has begun, and two additional tower cranes have appeared on the construction site.
🏗 Building 307
Excavation works have been completed, and pile foundation works have begun.
🏗 Standalone Parking Facility No. 22
Pile foundation works are 100% complete. Construction of the monolithic reinforced concrete foundations is now actively underway.